the transformer is going to be commissioned on 20111206, that is what the KSEB executive engineer nedumangad assures; thank goodness.
* * * *
andhakarathil ahalyayepole
it is almost three weeks
since the transformer has been hanging from the posts at kayapadi
not yet charged
not yet charged
FAX to KSEB
TRANSFORMER @ KAYIPADI
REQUEST EXPEDITE COMMISSIONING OF
* * *
Dr. Cheriyath Jyothi B.Sc., M.B.,B.S.,
theCloister
nr rockPark, venkode P.O., thiruvananthapuram - 695028
Consumer no.16209-0 kseb
No.2011/ele/memD november 28, 2011
REQUEST EXPEDITE COMMISSIONING OF
TRANSFORMER @ KAYAPADI
under vellanad section, thiruvananthapuram Dt.
as explained in the various letters ( including my letter no.201106/kseb/a dt. June 17, 2011 to the member distribution, handed over in person to the member's office ) and eMails and as evidenced by the accompanying photographs, the voltage of power supplied by the kseb over here is a disgrace to any civilised set up.
the installation of a transformer at kayapadi would have brought enormous relief to the locality. It was with a sigh of relief that ordinary mortals like me saw the work on the installation starting at last - the transformer had already been sanctioned long back..
But even after almost three months of starting work on the installation of the transformer, all that we have at the moment are the repeated shut offs of even the extremely low voltage current for most part of the day.
I am afraid the concerned authorities are dragging their feet on the matter.
IT SEEMS TO BE AN ENDLESS WAIT!
Could somebody, please, look into the matter and
COMMISSION THE TRANSFORMER WITHOUT FURTHER DELAY ?